Government Tightens Oil and Gas Block Extension Rules, Seeks Higher Profit Share

New framework covers seven Pre-NELP blocks, introduces stricter performance benchmarks, mandatory investment commitments and higher government revenue during extended production periods.

NEW DELHI: The government has introduced stricter conditions for extending production sharing contracts (PSCs) covering seven pre-New Exploration Licensing Policy (Pre-NELP) oil and gas blocks, linking longer production periods to higher government revenue, minimum operational performance and fresh investment commitments.

Under the revised policy, notified by the Ministry of Petroleum and Natural Gas on November 10, contract extensions can be granted until the end of a field’s economic life, subject to its continued commercial viability. Extensions may be approved in one or more instalments of up to 30 years each for both oil and gas fields.

A key feature of the new framework is an enhanced government share of profit petroleum during the extended contract period. The government’s share will increase by 10 percentage points above the rate determined under normal PSC provisions during the first 10 years of extension. The additional share will be five percentage points for the subsequent decade and 2.5 percentage points for the following 10 years. Normal contractual provisions will apply thereafter.

The revised framework replaces the policy issued in April 2017 and follows the notification of the Oilfields (Regulation and Development) Amendment Act, 2025, and the Petroleum and Natural Gas Rules, 2025.

The seven blocks covered under the policy include RJ-ON-90/1 and SGL (RJ-ON/6) in Rajasthan; Dirok AAP-ON-94/1 and AA-ONJ/2 in Assam and Assam-Mizoram; and Tarapur (CB-ON/2), Palej-Pramoda (CB-ON/7) and CB-ON/3 in Gujarat.

Application and approval process

Contractors will be eligible to seek an extension after completing half of their original contract period or its extended term. However, applications must be submitted at least two years before the existing contract expires.

The Directorate General of Hydrocarbons (DGH) will be required to submit its recommendation within six months of receiving an application. The government will subsequently take a decision within three months of receiving the DGH’s proposal.

Applicants must establish that sufficient recoverable reserves remain available to justify continued production. This requires a third-party reserves audit and submission of a field development plan or revised field development plan covering the proposed extension period.

The development plan must provide estimates of remaining reserves, projected production based on reservoir simulation studies, proposed operational activities and the expenditure required to implement the programme.

For development areas containing more than five million barrels of oil equivalent in remaining recoverable 2P/P50 reserves, the audit must be undertaken by an internationally reputed consultant selected from a panel maintained by the DGH.

Stricter performance and investment conditions

The revised policy places considerable emphasis on the previous operational performance of contractors. Applicants must demonstrate that they have fulfilled their development and production commitments during the preceding 10 years.

They must have either completed at least 70 per cent of the development wells specified in the approved field development plan or achieved a minimum of 70 per cent of the production committed under the approved field operating plan or work programme.

Contractors must also clear all outstanding statutory payments to the government, demonstrate adequate technical capabilities and meet the prescribed requirements relating to site restoration funds and restoration plans.

To ensure that investment commitments are fulfilled, the policy makes it mandatory for contractors to provide a bank guarantee equivalent to 10 per cent of the total estimated annual expenditure under the work programme approved by the Management Committee.

A grace period of up to one year may be permitted for completing delayed activities, provided the bank guarantee is extended and other prescribed conditions are satisfied.

Royalties and government revenue

During the extended contract period, contractors will be required to pay royalties and cess at prevailing rates applicable under the nomination regime. Their contributions will be calculated according to their respective participating interests.

The enhanced profit-sharing arrangement is expected to provide the government with a larger share of earnings from fields that continue producing beyond their original contractual periods.

By linking extensions to production performance, reserves availability and additional financial commitments, the government aims to ensure that continued access to hydrocarbon resources delivers greater economic returns.

Government retains right to reject extensions

The revised policy gives the government considerable flexibility in deciding the future of the covered oil and gas fields.

If existing contractors fail to satisfy the prescribed eligibility and performance requirements, the government can invite fresh bids for the blocks. Alternatively, it may assign the fields to national oil companies, including the Oil and Natural Gas Corporation (ONGC) and Oil India Ltd (OIL).

The government has also reserved the right to reject an extension request without assigning reasons and to introduce additional conditions depending on the circumstances of individual contracts.

Contractors unwilling to accept the revised framework will have their respective fields considered for fresh bidding on an as-is-where-is basis.

The policy further allows contractors to select the seat of arbitration in accordance with Rule 51 of the Petroleum and Natural Gas Rules, 2025.

Treatment of existing extensions

The government has clarified that extensions already granted under the April 2017 policy will remain valid until their respective approved expiry dates and will continue to operate under the existing terms.

However, all applications seeking a first extension beyond the original PSC period will be assessed under the new framework. The same conditions will apply to requests for additional extensions beyond periods already approved under the earlier policy.

The revised framework marks a significant change in the government’s approach to managing ageing oil and gas fields. By combining longer production opportunities with stronger performance requirements, higher profit-sharing obligations and enforceable investment commitments, the government intends to improve resource utilisation while securing greater returns from existing hydrocarbon assets.

Oil and Gas Block