SRINAGAR, OCTOBER 01: According to the Power Controller, Kashmir Province, Srinagar, in order to energize the repaired of 25 MVA Power Transformer, shutdown of 75 MVA, 132/33KV Lassipora GS on October 04 from 11am to 1PM.
Similarly, in order to carry out augmentation of Receiving Station Bemina II under IPDS srinagar and replacement of old 11kv VCB panels with fresh one, the receiving station Bemina II shall remain shutdown on October 03, 2020 from 9am to 5pm.
Further, in order to carry out execution of works under PSDF Scheme, the Receiving Station 120MVA,132/33 KV GSS Habak shall remain shutdown on October 03 from 9am to 4pm. Also, it shall remain shutdown on October 04, 05 and 06, 2020 from 10am to 4pm.
The power supply to the areas fed from these Receiving Stations shall remain affected on respective dates